Phase 2 Report

HRT Face-IV

Excavation:
The excavation of Face-IV has been successfully completed on 20th March 2017. The conventional method of Drilling and Blasting has been adopted throughout the whole stretch. Different classes of Rock have been encountered ranging from Poor to Medium Rock, which can be summarized as shown in Table 1.

RD(m)
Length    (m)
Rock Class
Remarks
From
To
1382.00
1390.50
8.50
Class-III
With Steel Ribs
1390.5
1405.25
14.75
Class-IV
Steel Ribs
1405.25
1414.25
9.00
Class-IV
Without Rib
1414.25
1416.50
2.25
Class-IV
Steel Ribs
1416.5
1419.5
3.00
Class-III

1419.50
1422.25
2.75
Class-III
With Steel Ribs
1422.25
1428.00
5.75
Class-III
Class-IV profile taken
1428.00
1436.25
8.25
Class-III
With Steel Ribs
1436.25
1460.50
24.25
Class-III
Class-IV profile taken
1460.50
1464.25
3.75
Class-III
With Steel Ribs
1464.25
1500.00
35.75
Class-III
Class-IV profile taken
1500.00
2096.00
596.00
Class-III

Table-1 Rock Classification of Face-IV

The details of the Excavation progress of Face-IV from January 2016 to March 2017 are detailed in Table-2.
Month
RD (m)
Length (m)
From
To
January-2016
1382
1404
22
February-2016
1404
1422.5
18.5
March-2016
1422.5
1456
33.5
April-2016
1456
1523
67
May-2016
1523
1574
51
June-2016
1574
1641.3
67.3
July-2016
1641.3
1700
58.7
August-2016
1700
1754
54
September-2016
1754
1796
42
October-2016
1796
1846
50
November-2016
1846
1894
48
December-2016
1894
1966
72
January-2017
1966
2019
53
February-2017
2019
2071
52
March-2017
2071
2096
25
Table-2: Details of monthly Excavation

Squeezing Zone:

Lower Class III and Class IV rock has been encountered between RD 1145 – 1422m along with consistent loose fall and cavity formation. On the recommendation of Geologist, Steel Ribs (ISMB 250) were provided for enhancing the stability of the profile. Later, in this area, due to high super incumbent cover, the presence of weak schistose rock, has resulted in squeezing condition. In several reaches, the steel ribs have deformed due to high stresses.
Total of 65 Nos. of steel ribs has been installed between RD 1382-1464m with 987.045 m3 of backfill concrete. Further, the profiles have been stabilized using channels (IS MC 100) as an umbrella and bracings.

Rib Rectification:

Upon the detailed survey of the squeezed zone, it was observed that the maximum settlement at crown was 28 cm at RD 1380m.
The invert was lowered by 50 cm at RD 1380 without disturbing the entire stretch of ribs at crown level in this zone and accordingly invert and overt lining was adjusted gradually from RD 1133 to RD 1520. The change in slopes is as shown in Table-3.
Further, the entire rib zone was evaluated for squeezing on RHS & LHS from the center line and following measures were taken at site: -
·         Where ever desired dimension of 3.4 m from the center line to rib flange is less than 3.4 m on both side, remining was done on both side to achieved desired section.
·         Where ever desired dimension of 3.4 m from the center line to rib flange is less than 3.4 m on one side and more than 3.4 m on opposite side, remining was avoided and the center line was adjusted to achieve the desired section.
·         Where ever desired dimension of 3.4 m from the center line to rib flange is less on one side and exactly 3.4 m on opposite side, remining was be done on one side only.

SL. No
INVERT
RD (m)
Original Elevation
New Elevation
Original Slope
New Slope
Remarks

Change in Slope from RD 1133 – 1380m

1
1133
1698.84
1698.84

1 in 198.86

1 in 141.79
RD 1133-1380
New Slop 1 in 141.79
2
1380
1697.6
1697.10
Change in Slope from RD 1380 – 1520m
3
1380
1697.6
1697.10
1 in 198.86
1 in 686.27
RD 1380-1520
 New Slope 1 in 686.27
4
1520
1696.89
1696.90
Table-3: Details of Change in Slope
  
Overt & Invert Lining:

The overt lining of Face-IV started on 18.05.2018. A total length of 2346 m of HRT Overt lining was done from Face-IV deploying four Gantries at a peak time. The last Gantry at the Adit junction was done on 26.10.2018. The details of the monthly progress of Overt Lining can be figured out from Table-4. Two Hydraulic kerb shutters (6 m each) was deployed for improving the progress of the Kerb concreting. Modified kerb shuttering was adopted along with modified Gantry for minimizing the joints (joints between kerb and gantry).

Invert concreting of 2319 m was started on 06.02.2018 and successfully completed on 12.11.2018 with the concreting of Adit Junction. Initially, Invert Scatter was used for Invert concreting which was later stopped due to slow progress. Manually, using the Invert Template was adopted for Invert Concreting. The monthly progress of Invert concrete was tabulated in Table-5.

SL. No
Month
Length (m)
Remarks
SL. No
Month
Length (m)
Remarks




1
May-17
46.4

1
Feb-18
439

2
Jun-17
117.7

2
Mar-18
185

3
Jul-17
14.8

3
Apr-18
226

4
Sep-17
28

4
Sep-18
423

5
Oct-17
148

5
Oct-18
1016

6
Nov-17
102.5

6
Nov-18
30





Table-6: Details of Invert Lining
7
Dec-17
211


 8
Jan-18
206.5


 9
Feb-18
59.4


10
Mar-18
309.9


11
Apr-18
88.8


12
May-18
150


13
Jun-18
426.9


14
Jul-18
114


15
Aug-18
103.6


16
Sep-18
189.9


17
Oct-18
28.6


 Table-4: Overt Lining Details

RCC Lining:
RCC lining was provided for 255 m stretch between RD 1145 to 1400 m. Double layer of reinforcements was provided with 25 mm dia @ 200 c/c as a main bar and 16 mm dia @ 200 c/c as distribution bar.


PS: Mailed to EE sir for further correction and necessary action.